Overview of Status of Analysis, Design, Fabrication, Tests, etc.
We are currently in the brainstorming phase for our design.
Accomplishments from Previous Week
N/A. This is our first week meeting.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Brainstorming for next meeting with sponsor - to be conducted by every member:
Various existing approaches and technologies to measure stress and strain (can be biological tissues or non-biological tissues)
3 examples (or more)
A tentative list of constraints that you think may be relevant to an eventual design.
5 examples (or more)
Will spend 5 minutes each explaining our findings in the next sponsor meeting
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Held the kickoff meeting:
Introduced ourselves
Went over the general overview of Dr. Shah’s background and how it ties into this specific project for 156B
Discussed specific objectives for the bigger scope of the project and defined primary, secondary, and the “wow” objectives
Defined the objective for risk reduction and how it contributes to the development of the project
Tasks explained in the “next steps” section
Went over the budget and any purchasing guidelines
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Had yet to conduct kickoff meeting at time of first meeting with instructor
Went over plan for preliminary research
Advised to look at past projects conducted by Dr. Shah
Hoped to have kickoff meeting before next instructor meeting (accomplished)
Risks and Areas of Concern (i.e. show stoppers)
Still in the brainstorming phase so no concerns yet.
Resources or Information Required but not Available
N/A
Schedule
Research approaches to measure stress and strain.
List any constraints the device would have.
Update Gantt chart.
Budget (list amount spent and amount remaining)
Amount Spent: $0
Amount Remaining: $2600
Progress on Report and Webpage
N/A.