Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Spray mechanism design in progressÂ
Looking for a manufacturer for the atomizer
Accomplishments from Previous Week
Completed analysis on each spray mechanism we design and performance demonstration
Ideal sprayer schematic design in mind
Detail material testing performed
Analysis and demonstration of material choices made
Final report 50% finished
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize atomizer design
Look for and discuss with potential manufacturer resource
Successfully manufacture ideal atomizer design
Optimization on the anesthetic loss
Risk reduction test on the new spray tip
Analysis on performance result
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Sponsor was satisfied with the project progress
Sponsor demands animation for the design and detailed component information
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Good progress on the project
Instructor provide useful manufacturer resource for advices
Risks and Areas of Concern
The material choice of the new spray tip
The performance of the atomizer
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Implementation on the atomizer produced by manufacturer
Update Gantt chart.