Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Proposed design solution has been made.
The implementations of the design prototype with a smaller scale (compare with risk reduction prototype) to match the required dimensions are in progress.
Implementation of component solution (spray and retraction mechanism) in progress
Accomplishments from Previous Week
The 1st design has been finalized as the current approach out of the three preliminary designs
Specific required dimension on design has been settled
Justification of key decision on board design and components has been made
Finalized further design decisions that need to be made in further
Integration meeting with the sponsor regarding future approach has been made
Design proposal presentation has been settled
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Start purchasing major components needed for the design solution
Start developing an advanced prototype with required dimension
Readjust specific dimension
Implement spray and retraction mechanism design idea
Machine all items that are needed for the two mechanisms above
Analyze the implementation result
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
The meeting with the sponsor was delayed to take place on Tuesday afternoon due to schedule conflict.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Clearer images should be made for presentation
The administration of anesthesia for the intubation process should have been shown to audiences.
Simple 2D drawing can be created on each concept with descriptive names
Risks and Areas of Concern
Effect of potential difficulties on retraction design
Amount of anesthesia lost in the laryngotracheal tube
Difficulties of purchasing or manufacturing the component in desired small scale
Possible contaminations with the aluminum stylet?
Any protective layer can be added on the design surface to prevent potential damage to patient soft tissue due to hard material.
Resources or Information Required but not Available
N/A so far.
Schedule
Describe upcoming milestone
Complete implementation test on spray and retraction mechanism
Update Gantt chart.