Made key design decision of using Silicone tubing for vein.
Preliminary research results from the task into two “mini” teams to focus on 1) pressure delivery system and 2) skin/flesh manufacturing.
Accomplishments from Previous Week
Preliminary research results on the overview of casting/moulding.
CAD of mould for muscle system.
Preliminary research results on pressure system.
Met with Dr. Ryan to confirm our methods for casting.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
For Rahaf and Reem:
Still need to get George to send me his experimental process (Rahaf, send request again).
Visit Machine shop to confirm the creation of the mould.
Finalize material selection and order parts.
For Cecily, Samantha, and Guinevere:
Research over different types of pumps and determine which are potential options.
Start ordering pumps online.
Design a system with [two] blood pressures for vein and artery.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Confirmed approach with Dr. Ryan → attach holes in the design of the mould to release air.
Dr. Ryan encouraged us to think about the end-user and constantly think about “how many times are they planning on doing ECMO per year? Would silicone be worth it given cost constraints?”
Helped with research keywords such as “ballistic gelatin”; provide practical advice on making gelatin models (spray oil before casting/ consider materials shrinking/ store in fridge to keep moisturized)
Check Reddit DIY community for help on casting.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Comments:
Reach out to sponsor and schedule meeting on weekly bases.
Think of latex-dipping for vein.
Add comparison table to show why we chose silicone for veins.
Actions:
Had a sponsor meeting on Monday morning to discuss moulding and casting methods.
Justified why using silicone for veins in the design proposal presentation.
Risks and Areas of Concern
Moulding and casting seems to be an experimental and “trial and error” approach.
Schedule
Next week:
Order materials
Meet with machine shop
Budget (list amount spent and amount remaining)
Total Budget: $6000
Total Remaining at beginning of week: $5956.71
Total Spent this week: $0
TOTAL REMAINING AT END OF WEEK: $5956.71
Total spent to date: $43.29
Progress on Report and Webpage
Will begin with the Week 2 sections of the final report this week