Finished Risk Reduction process.
Picked Silicone tubing for vein.
Divided task into two “mini” teams to focus on 1) pressure delivery system and 2) skin/flesh manufacturing.
Accomplishments from Previous Week
None yet. During break, we went over the Risk Reduction slides with our sponsor.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Research pump, fluid mechanics back-end computation (Samantha, Guinevere, Yichen)
Asked George for instruction on how they built skin mold (Rahaf). Upon receiving details, will research ways to improve and optimize method (Rahaf and Reem).
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Watched doctors and nurses participate in ECMO simulation.
Given more supplies and dimensions for veins and arteries.
Fixed minor edits on Risk Reduction slides.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
N/A
Risks and Areas of Concern
Time to wait for delivery (2 weeks).
Figuring out how to improve the current process for creating the skin mold.
Maintaining vein and artery tube shape while pouring silicon.
Quicker than previous method.
Schedule
Next week:
Continue risk reduction experimentation
Finish research into the two sub-topics (blood pressure & skin manufacturing)
Budget (list amount spent and amount remaining)
Total Budget: $6000
Total Remaining at beginning of week: $5956.71
Total Spent this week: $0
TOTAL REMAINING AT END OF WEEK: $5956.71
Total spent to date: $43.29
Progress on Report and Webpage
Website is available.