Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Decided plan for installing galvo system.
High speed camera and driver boards are already installed.
Triangulation for low speed cameras are done.
Accomplishments from Previous Week
Manufactured the breadboard.
Installed high speed camera and driver board.
Purchased components used for installing galvo.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Installed the galvo system and finish wire connection.(Mingcong and Zizhao)
Align galvo system and high speed camera. (Mingcong and Zizhao)
Finish low-speed cameras tracking and setting up DAQ code (Keren)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Edge of breadboard will influence the view of galvo, and we should develop the plan for avoiding this problem.
We should develop the plan for aligning galvo and high speed camera.
Actions: We finally decided to drill a hole on breadboard to avoid the influence of edge of breadboard. And we talked with Dr.Dhruv Grover and knew that we could use laser device for aligning.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
We should discuss high-level purpose for our project with Dr.Gravish and add ultimate goal in our report.
We should not write long paragraphs for deliverables.
Actions: We will ask Dr.Gravish about high level purpose during the meeting on Tuesday. And we change the form of our deliverables in bullet point form.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
None.
Resources or Information Required but not Available
None
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Last week: $177.47 (AP90RL - Large Right-Angle Bracket)
Progress on Report and Webpage
We will finish 50% of our report.
We finished the proof of concept presentation.
We updated our internal page.