Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finalizing Design for Risk Reduction Hardware Test
Individual Component Analyses in progress
Began working on Risk Reduction Presentation Slides
Set up team website!
Accomplishments from Previous Week
Obtained balloons and duct tape for risk reduction hardware test
Obtained workspace on campus
Transported prototype from Hillcrest Medical Center to campus workspace
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Order neoprene sheets and silicone for risk reduction hardware test
Conduct hardware test
Finish Risk Reduction Presentation
Finish Individual Component Analyses
Finalize weekly meeting time with sponsor for next quarter
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Determine meeting time for next quarter (in person) - set up a when2meet to see when all team members are available for meetings
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Begin sourcing materials for risk reduction hardware test (in person) - obtained balloons and duct tape, in process of determining what thickness of neoprene and what type of silicone to order
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Shipping time for risk reduction materials ordered online
Resources or Information Required but not Available
Where to buy stock silicone - current choice is to buy silicone for mold-making
Schedule
Upcoming milestones: Risk Reduction Hardware Test and Individual Component Analyses
Budget (list amount spent and amount remaining)
Amount Spent ($1.50 total)
$1.50 - Balloons
$0 - Duct tape (already in possession of some)
Amount Remaining
$1998.50
Progress on Report and Webpage
No formal progress on Report
Webpage has been set up
Began Weekly Project Updates