Weekly Progress Report
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Tested the final design (05/19)
Accomplishments from Previous Week
Finished fabricating the sled
Successfully tested the final design at Fiesta Island (05/19)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Paint the sled (Hanh and Paulina)
Present results from the last test to sponsor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Sled worked well and performed all required functions
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Add belleville spring to cable braking system
Risks and Areas of Concern
None
Resources or Information Required but not Available
Remind Professor T. to talk to Mark about how the donation to pay for project will work and what the timeline will look like for it
Schedule
Analyze data from the last test
Present to sponsor
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent $630
Remaining $3370
Progress on Report and Webpage
Second Draft of Report has been sent in
Webpage been updated
Initial files and presentation uploaded
Cover page executive summary added
Some photos from previous tests have been uploaded