Weekly Progress Report
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Tested the final design (05/19)
Accomplishments from Previous Week
Started painting the sled
Added a belleville washer
Made housing for water jet
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish painting the sled (Group)
Present results from the last test to sponsor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Sled worked well and performed all required functions
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Add belleville spring to cable braking system
Risks and Areas of Concern
None
Resources or Information Required but not Available
Schedule
Analyze data from the last test
Present to sponsor
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent $870
Remaining $3130
Progress on Report and Webpage
Second Draft of Report has been sent in
Webpage been updated
Initial files and presentation uploaded
Cover page executive summary added
Some photos from previous tests have been uploaded