Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Risk reduction fabrication almost complete
Finish blade manufacturing
Need to get materials for test from Mark
Winch, pulley, barbells, duck bill anchors, load cell, battery, synthetic rope, sledge hammer
Accomplishments from Previous Week
Risk reduction fabrication began
Sponsor approved of risk reduction method
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish Risk Reduction fabrication (Joe and Zak)
Finish Risk reduction test (All)
Get started on website (Paulina)
Get Presentation Ready (Hanh)
Analyze data from test (Zak)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Develop test plan
Talk to soil mechanics professor
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Clarified budget
Discussed blade attachment mechanism
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Not Applicable
Risks and Areas of Concern
Cable feeding system
First test not working
Resources or Information Required but not Available
Not Applicable
Schedule
Finish fabrication 3/8/16-3/10/16
Meet with Mark 3/11/16
Perform risk reduction test 3/12/16
Analyze results and prepare presentation 3/12/16-3/15/16
Budget (list amount spent and amount remaining)
Spent: around $250
Student Budget left: about $750
Sponsor Budget left: $3000
Progress on Report and Webpage
Initial Parts of Webpage have started