Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Stirring Stage - completed the stage and tested with operating motor, currently under start of testing
Bioreactor - final components have arrived and been installed. Ready for testing.
Tilting Stage - near completion (75%). Final welding is largest obstacle remaining.
Accomplishments from Previous Week
Remaining bioreactor parts arrived. Prototype finished.
Stirring stage tested with operating motor and rotational path with linear guide rails confirmed .
Tilting stage: slotted rings fabricated, holes drilled in base plate.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Complete testing prototype (EVERYONE)
Weld hinge plates to top plate (ISAIAH/JORDAN,RYAN)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Looking forward to seeing completed prototype.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Motor to crank connector: followed instructor's advice and bolted part to crank.
Risks and Areas of Concern
Isaiah (welding). Have yet to discuss welding agenda for next week.
Resources or Information Required but not Available
Schedule
Complete testing asap.
Budget (list amount spent and amount remaining)
Amount spent: 3,035.62
Amount remaining: -35.62
Progress on Report and Webpage
Budget and Parts sections have been updated on the website.
Report is in the final stages.