Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Initial prototype machined from delrin completed
Design of U's and Dots semi-finalized and ready for prototyping data transfer
Accomplishments from Previous Week
Finals Week/Covid Survival
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Call/Email Fuzz Button Company re: Currently in production runs to avoid tooling costs - Harald
Call/Email DigiKey re: Supply issues and lead times - Harald
Finalize Locking Mechanism Design
Choice between 1 Custom and 2 Existing Solutions - Trent/Jesse
Finalize material choice and contact print houses for estimates - Trent/Jesse
Re3D Tech - https://re3dtech.com/3d-composites/3d-printed-6061-7075-aluminum/
Call/Email for 100x100 plate comps
Setup Meeting w/Steve Roberts for Monday 4/6/2020 - Leigh/Jesse
Initial PCB Design using Eagle/Altium - Leigh/Jesse
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Contact/Post questions to the team Slack so that consulting engineers can provide feedback
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Consider 7075 Al in place of 6061 Al if considering tapping threads as 6061 is too weak/may cause galling - via Zoom presentation
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Lead times for manufacturers may be extended by Covid-19 Pandemic
Lack of machine shop may cause issues with design revisions etc. due to lack of rapid prototyping facilities (e.g. 2-day vs 2-week)
Scope of project may be narrowed or changed in several ways
No machinable prototype may mean that all work done digitally in CAD
Exos Aerospace has been nonresponsive re: launch window etc.
Resources or Information Required but not Available
Dimensional constraints for packaging, design and assembly in the rocket.
Requirements for data transfer and protocol
Machine design tolerance allowed
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage