Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Status of Analysis:
Exploring all the FEA tests that can performed on Fusion 360, SolidWorks, Ansys that may help us get closer to structural strength
Point - impact tests
Cutting tests
Planning out usability tests one 3D printed model is shipped to us
Status of Design:
We have a working prototype for the outer shell of our box.
Currently generating ideas for the looping mechanism and assessing design trade-offs
Reverse engineered locking mechanism from MasterLock reference lock to assemble it into our prototype
Status of Fabrication:
We have set up a meeting with Chris Cassidy for getting our working prototype 3D printed
Our sponsors have contacted a manufacturer in Tijuana to fabricate the prototype for us. We will be having a meeting with them sometime within the next week or two.
Accomplishments from Previous Week
Closed on the outer design of the working prototype. Re-assessed timeline and increased internal meeting frequency to at least one meeting a day.
Conducted meeting with Tom Chalfant and Steve Mersack for insights on developing looping mechanism
Conduced meeting with Chris Cassidy to get 3D printed parts
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Friday meeting with Chris Cassidy: Get our design 3D printed and shipped out to Bryan. - All team
Implement the MasterLock locking assembly in our 3D printed design and ship it to the sponsor. - Bryan
Receive sponsor feedback and make immediate changes to our shell design. - All team
Finalize locking and looping mechanisms. - All team + sponsor
Talk to Prof. Delson and other knowledgeable folks to figure out different simulation tests that would be useful and applicable. - Hrish
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
28 April: Sponsor seems generally satisfied with the outer shell of the lockbox. Sponsor realized that the 156B team is running out of time and needs to move faster. As a consequence, internal meeting frequency was increased to reduce iteration time.
Sponsor is awaiting a satisfying solution to the looping and locking mechanism. Sponsor communicated some ideas for looping mechanism which were later determined to be difficult to implement in a meeting with Tom Chalfant and Steve Mersack.
Meanwhile, sponsor clarified the details of the Tijuana manufacturing firm, suggesting that the turnaround time would be approximately a week after receiving the final design.
Next sponsor meeting set for Sunday, 3 May 2020
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Two of the teammates could not attend the instructor meeting so it was pushed to Monday, 4 May 2020.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
General tone of comments presented from presentation were as follow:
"Good presentation and graphics"
"Needs more analysis for outer shell and design"
"Team has made progress but needs to make more progress"
Risks and Areas of Concern
Locking mechanism has highly precise parts that may not be able to be machined or mass-produced
Current looping mechanisms being developed after conversation with Tom and Steve have usability trade-offs that the sponsor may not approve of
(same as last week) Exposure of spaces near the hinge are could make the lock more prone to be broken into and hence we need tighter tolerances.
(same as last week) Making the handle adjustable might be not feasible and could have a limited life cycle.
Resources or Information Required but not Available
How to make SolidWorks, Fusion 360 etc. simulation choices?
Schedule
Describe upcoming milestone:
Looping mechanism figured out and approved by sponsor
Update Gantt chart.
Budget (list amount spent and amount remaining)
Allocated: $2000
Spent: $100
Left: $1900
Progress on Report and Webpage
Webpage updated with design
Report writing commenced. First draft of report due this weekend.