156B Week 8
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Locking mechanisms fully machined and need to be integrated
RFID is being tested and needs to be integrated
Final design of station needs to be assembled and tested
Accomplishments from Previous Week
Locking mechanisms fabricated
Performed user testing with The Walker
Researched and analyzed cost of aluminum extrusions for station design
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Integrate RFID with rest of system - Amber, Jason
Order materials - Nic
Integrate locking mechanisms - Eric, Amber
Assemble station - Everyone
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Our sponsors and the team set out to perform some user testing on the beach, all the while receiving feedback on the already existing station and similar designs.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor has suggested using Schedule 80 PVC piping for the station. We have discussed within ourselves and with our sponsors and decided on using 8020 aluminum extrusions.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Fully assembled station integration with locking mechanisms
Resources or Information Required but not Available
Schedule
Integration into final design by next weekend.
Budget (list amount spent and amount remaining)
769.61 spent
1230.39 remaining
Progress on Report and Webpage
Front page updated
Progress report updated
Rough draft of report updated