Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Printed additional hand grips (this time with the Connex3 printer)
Accomplishments from Previous Week
PCB and electronics box parts are ordered and set to all arrive by Thursday, will begin assembly Thursday/Friday
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Complete the hardware assembly (Team)
Work on report and poster (Team)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor asked us to characterize the rise time of the signal so we are doing that once we get the PCB assembled
Sponsor asked us to not route cables through holes on the box, but rather to have connectors mounted to the electronics box
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
None
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
None
Resources or Information Required but not Available
When are the poster/website actually due? There appear to be two different dates on the website schedule.
Schedule
Assemble PCB and electronics box (Week 9/10)
Final Calibration (Week 10)
Characterize rise time of signal (Week 10)
On track with the Gantt Chart
Budget (list amount spent and amount remaining)
Spent $366.61 of $600 part budget ($233.59 remaining)
Spent $8.93 of $100 3D printing budget ($91.07 remaining)
Spent $0 of $600 part budget ($600 remaining)
Progress on Report and Webpage
Report draft 2 is submitted and being reviewed by Young. Nearly done with the content of the report, will review after we receive final comments.
Webpage is being updated.