Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Hardware is fully assembled
Accomplishments from Previous Week
Electronics box and PCB are both fully assembled
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish up report, poster, and webpage (Team)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Calculated the rise time per the sponsor's request
Mounted connectors to the box per sponsor's request
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Editing poster and report per Instructor comments
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
None
Resources or Information Required but not Available
None
Schedule
Finish up report (Week 10)
Finish up poster (Monday, Finals Week)
Print report (Monday, Finals Week)
Finish up webpage (Wednesday, Finals Week)
Clean up lab space and get formed signed off (Wednesday, Finals Week)
Poster session and delivery of parts (Thursday, Finals Week)
Budget (list amount spent and amount remaining)
Spent $390.38 of $600 part budget ($209.62 remaining)
Spent $8.93 of $100 3D printing budget ($91.07 remaining)
Spent $0 of $600 part budget ($600 remaining)
Progress on Report and Webpage
Report has all content and is nearly done being edited
Webpage is being updated
Poster was edited per comments