Overview of Status of Analysis, Design, Fabrication, Tests, etc.
We have narrowed down our design options: flexible force sensors, multi-axis strain gauge, and mechanical transmission
We have decided on individual components analysis topics to study
Accomplishments from Previous Week
Read through the papers supplied by our sponsor and found on the internet to gather information on approximate loads to design for, past work, etc.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Work on individual analysis (team)
Email sponsor and Sam to ask for further clarification about frequency response, FlexiForce sensor accuracy per discussion with Ben (Rachel will initiate)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor connected us with collaborators and other potentially helpful individuals and we've reached out to them and received responses
Sam Ward - collaborator
Brazil Team - collaborators
Ben Krasnow - engineer
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
no comments were made
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
no comments were made
Risks and Areas of Concern
MRI environment continues to be our largest risk source
Resources or Information Required but not Available
Need to ask sponsor for clarification on his comment about the frequency response of a water-based system
Need to clarify with sponsor's collaborator about accuracy/repeatability needs
Schedule
Gantt chart is updated HERE
Next Milestones:
Individual Component Analysis (due Friday of Week 1)
Design proposals (Week 2)
Budget (list amount spent and amount remaining)
None Spent
Progress on Report and Webpage
Progress reports are being filled out
Gantt chart is being updated
Team page is finished except for changes to team member pictures
Home page is pending further work once we have more on our project