Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Accomplishments from Previous Week
Fabricated interior frame, which means cut 14 acrylic plates on the lasercam, cut 40 spacers, cut and threaded 6 aluminum rods. (Tyler)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Completely fabricate Snowcam
Waterproof test
Test for stability
Buoyancy test
Test progams
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Sponsor wants a recent fluid simulation. CFD simulation on current Snow-Cam design done (Jamie)
If all goes well, there may be a overnight expedition in mid-march. Which means we should build the Snow-Cam this week!
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Budget (list amount spent and amount remaining)
Progress on Report and Webpage
Report writing and webpage on the back burner. Plan on adding pics of completed Snow-cam and making corrections this weekend.