*156B Week 7
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Started Fabrication on arms and motor mounts
Waiting for Half-pipe material
have not started building half-pipe yet
Ordered rest of components
remote, arduino, potentiometers, wires, raw materails
Accomplishments from Previous Week
Ordered the rest of the raw materials
Ordered the rest of the electronics
Ordered half-pipe materials
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish robot fabrication
Daniel: fabricate motor mounts and bulk-head
Tallha:fabricate arms
Beth: fabricate center structure
Nelson: start half-pipe construction- finish by Saturday
Hannah: Finish working model analysis
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No meeting w/ sponsor
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No comments concerning robot
clear up problems in report
Set up sponsor meeting for first week in June
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Lead times on orders (small concern)
Two day delay added to shipping when ordered through school
To solve, will pay for 1-day shipping on crucial components
Resources or Information Required but not Available
none
Schedule
Have robot assembled by Saturday
Update Gantt chart.
Budget (list amount spent and amount remaining)
$400 spent on raw materials
total spent $1400
$600 of $2000 left
$2600 of $4000 left
Progress on Report and Webpage
Prototype 2 CAD uploaded
Old half-pipe photos uploaded
Prototype 3 WaterJet Cad Uploaded
New half-pipe Cad Uploaded