156B Week 10
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Fabrication finished
Electronics finished
Programming Finished
Testing Finished
Accomplishments from Previous Week
Finished Programming
Finished Testing
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Everyone: Finish up poster for poster presentation
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
None
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Grind down screw which was adding friction to system
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
none
Risks and Areas of Concern
none
Resources or Information Required but not Available
none
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$1500 spent total
Progress on Report and Webpage