156A Week 10
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finished prototype. Working out small problems
Finish prototype programing
construct appropriate sized half-pipe for successful test
Accomplishments from Previous Week
Finished finalized design
Finished base prototype
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish prototype and half-pipe for demo on Monday 19th
Create presentation for Monday
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Finishing on Time
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$172 for half-pipe materials
Progress on Report and Webpage