SEQUENCE STATUS: IN PROGRESS
START 03/22/21
COMPLETED WORK (as of 11/16/21)
-Walls constructed to change the open basement space into new separate rooms
-Drywalling and painting completed
-Doors added to new basement rooms
-Glass storefront added to new booksale are
-Archive and archive reading room beginning to take shape
FLOOR PLAN (PINK)
PROGRESS PICTURES
some provided by KrM Architects