New Addition

SEQUENCE STATUS: IN PROGRESS
START 01/04/21
DURATION: 12-14 MONTHS

WORK COMPLETED (as of 11/16/21)
-Temporary wall constructed inside the library to separate the expansion work from the main areas of the library
-Demolition of library amphitheater and former public seating area
-Steel beams installed to create frame of addition
-Concrete poured for all floors
-Framing is done for interior rooms
-Framework for new stairs awaits concrete pour
-Limestone base around perimeter is being installed
-Drywalling has been done, with finished areas beginning to take shape

FLOOR PLANS

PROGRESS PICTURES
some provided by KrM Architects