SEQUENCE STATUS: IN PROGRESS
START 05/03/21
DURATION: 8 WEEKS
WORK COMPLETED (as of 8/16/21)
-First floor collections moved into temporary locations
-Shelving units adjusted or moved
-Old information desk, copy counter, OPAC counter, computer stations, and displays are moved and/or disposed
-New bulkhead and window slats constructed in location of new main desk
-Old carpet removed
-New carpet installed
-Temporary main desk assembled and functional
FLOOR PLAN (LIGHT BLUE)
PROGRESS PICTURES
some provided by KrM Architects