2019 Off the Grid

Deming High School competed this year. 

The game field represents a damaged electrical grid that needs repair.  The field includes a diagonal row of high voltage towers where 345KV power lines need to be installed to complete multiple circuits.  On the center tower there are poles where 138KV power lines need to be installed to bridge between the high voltage transmission lines and other areas of the grid.  Large square substation transformers are needed near the edge towers for the high voltage line and near the 138KV poles.  Conduit is to be installed in underground trenches (surrounded by ramps) that allows the connection of 13KV circuits to the periphery of the field.  Distribution power poles near houses along the edge of the field provide support for 4KV power lines.  The installation of cylindrical residential transformers is also needed on the power poles near the houses.  In addition to installing and repairing the grid components there is debris cluttering the area that needs to be removed. As a new twist to this year�s game robots are also tasked with autonomously delivering spare insulators from the starting area to one or more of the high-voltage towers. 

Most scoring areas are shared and are accessible by all teams on a first-come basis. Only the following scoring areas are assigned to a specific team:

To allow proper identification of which team scored in the common scoring areas many of the team-assigned game pieces are color coded to match the team.  A summary of the shared and team-assigned game pieces is contained in the table that follows that also details the initial location of the game pieces. 

Other than autonomous delivery parts (discussed later) scoring is based on the position of the item at the end of the match. The 345KV and 4KV lines are scored based on the number of segments that have been properly installed where a segment is supported by two hooks/insulators. The 138KV lines are scored per connection made but the second connection must be to the corresponding spot on the opposite pole. Conduit must lay flat within a trench to score.  Transformers are scored by either being properly installed in the base pad or mounted to the residential pole depending on the type of transformer. Ground debris can be scored by placing it into the staging area or into the debris bin.  Point values for the various scoring actions are detailed in the table that follows. 

Autonomous scoring can happen at any point during a match.  Although black and white roads are provided to help robots find their way to the scoring towers, robots are not required to follow the lines.  The sequence required for a robot to make an autonomous delivery attempt is summarized as:

The following bonus score opportunities exist in addition to the scoring elements previously described:



Residential Lines - Installed

Transformer Skid