DETAIL engineering (connections design)
Design of main steel-to-steel connections in IDEA StatiCa according to NBN EN1993-1-8
Preparing Joint Design official report (Dutch)
ESTIMATION: 40 Hrs (as FIX hours)
NOTES: (Engineering)
Connections to the concrete and anchor connections are not included in this offer.
These estimations are based on the received IFC model any additional information of change in geometry or structure will provoke changes in the Fix hours.
These estimations are based on the fact that calculation model will be delivered (SCIA or DIAMONDS/) with generated ULS/SLS combinations.
In this estimation 1 coordination meeting of 1 hour is included
Time schedule will be mutually agreeable after / upon receiving confirmation or purchase order.
Earliest start: Week 32
TEKLA detailing
Modeling of all the steel structures ( structural, handrails, cage ladders, stairs, , gratings)
Phase 1: Structure inside existing building ( under the roof)
Phase 2: Remaining steel structure
GA drawings (max. 2 revisions)
Production drawings package
Anchorchairs not included.
ESTIMATION: 75 Hrs (as FIX hours)
NOTES: (Tekla detailing)
These estimations are based on the received IFC model any additional information of change in geometry or structure will provoke changes in the Fix hours.
Taking and implementing site dimensions are NOT anticipated in this offer.
Support steel for facades and roof panels is not included in this offer.
In this estimation 1 coordination meeting of 1 hour is included
Time schedule upon receiving confirmation or purchase order on week 32 or earlier.
31 st of august : Finished production package for Phase 1
7th of september: grating drawings.
13th of September : Complete production package of phase 2