South Stirling Gateway allocation within the Stirling Local Development Plan (LDP) first mooted in Draft LDP in October 2011
South Stirling Gateway allocation confirmed within the Stirling LDP adopted in September 2014
South Stirling Gateway allocation re-confirmed within the revised Stirling LDP adopted in October 2018
Application for Planning Permission in Principle (PPiP) submitted in December 2018
PPiP application report to Stirling Council Planning Committee June 2020
Section 75 agreement concluded and PPiP issued November 2022
First Application for Matters Specified in Conditions (AMSC) submissions made in December 2022
Initial remedial works (grouting) began in May 2023
First AMSC submissions reported to Stirling Council Planning Committee in the last quarter of 2023
First of further applications for remaining land submitted to Stirling Council in September 2023Â (further info available here)
Site start (infrastructure and earthworks) in September 2023
Site start (housing first phase) in February 2024
Sales complex at Brucefields opened in September 2024 (sales info available here)
New Pirnhall Road / A91 Junction completed 31 March 2025
First occupations (house sales) targeted for April 2025
Work on building the new primary school scheduled to start May 2025
New primary school (by Stirling Council) due to open August 2026