500 Piety St.

District: Bywater - Full Control 

Owner: Schoen Fuselier 

HDLC Staff: Chase Klugh 

Rating: Non-Contributing 

Applicant: Concordia 

Permit #: 19-18409-HDLC

Description: New construction of a six-story mixed-use building on a vacant lot. Massing and design changes to previously-approved five-story mixed-use commercial building proposal.

Staff Recommendations: 

The proposed six-story hotel building at 500 Piety Street is situated adjacent the Rusty Rainbow bridge on the river side of Chartres Street, overlooking Crescent Park. First reviewed by the HDLC Architectural Review Committee (ARC) in 2019, the building's siting, massing, and overall design have developed through several different iterations. As reflected in the ARC's comments and previously proposed drawings below, the project has experienced maturation throughout this process. Although the design reviewed in March 2022 received ARC recommended approval, massing alterations at the roof top that effectively created a six-story, required additional review and comment by the ARC. Review of these changes began in July 2023 and have continued throughout the latter months of this year. Throughout that time, the focus remained on the massing of the fifth and sixth floors as well as three-story steel frames at the eastern and western entrances. At the September 19, 2023 meeting, the ARC agreed that the easterly-facing entry frame should be reduced to two-stories, but that the westerly-facing frame could remain at it proposed height. At the October 17, 2023 ARC meeting, the Committee agreed that the reduction in height and massing of the fifth and sixth floor were successful. However, a standing recommendation that the proposed steel frame at the eastern elevation be reduced to two stories in height could not be agreed upon. The October meeting for 500 Piety Street ended in a no action vote after the ARC could not come to a consensus on the inclusion of the three-story framed metal entry. The vote was two (2) yeas to one (1) nay. 

The applicant is petitioning the Commission to make a determination regarding the proposed steel framed entry at the easterly-facing entrance. The trepidation of ARC members stems from the standpoint that a three-story frame attached to the building at this elevation visually competes with the Rusty Rainbow bridge. The October ARC proposal included a reconfiguration of the eastern elevation to move the entry (and three-story frame) approximately 30'-0" from its original location, closer to Chartres Street. This shift also centered the entry on the existing parking lot. The applicant's request is grounded in the need for space to display public art; a theme integral to the conceptual design of the building. Although it remains undetermined, the proposed three-story steel frame will be the host of some form of suspended artwork. Because the ARC could not make a full-consensus recommendation, Staff leaves the decision at the discretion of the Commission. 


ARC and Commission Review Timeline: 

Previous ARC Recommendations: 

10/17/23:

09/19/23:

07/18/23:

03/22/22:

02/15/22:

07/23/19:

06/18/19:

Context Photos:

Elevation Comparison Over Time:

Proposal that was approved in March/April 2022: 

July 2023 submission of fith and sixth floor massing alterations: 

Current Drawings:

2023.12.06_Crescent Hotel_DesignReview.pdf

Previous Drawings - 10/2023:

2023.10.17_Crescent Hotel_ARC Review.pdf

Previous Drawings - 09/19/23:

2023.09.14_Crescent Hotel_ARC Review.pdf

Previous Drawings - 07/18/23:

2023.06.30_Crescent Hotel_HDLC Review.pdf

Previous Drawings (Received ARC Approval) - 03/22/22:

ARC Piety Presentation 5.pdf

Previous Drawings - 02/15/22:

Crescent Hotel_ARC Piety Presentation-compressed.pdf

Previous Drawings - 07/15/2019:

500 Piety - Hotel ARC Submission_July_2019.pdf

Previous Drawings - 06/07/2019:

500 Piety - Hotel ARC Submission_July_2019.pdf

Street View: