Milestones

Fall 2018

Milestone: Deliverable -- Due Date

Define customer expectations: List of expectations -- September 21st

Analyze road-side drying: Report on road-side drying -- September 21st

Research current drying methods: Report on grain drying methods -- September 28th

Brainstorm and select drying method: Decision matrix & explanation of choice -- October 12th

Prototype design & expected performance: Sketches & calculations -- October 26th

Finalize design & expected performance: CAD Files & Calculations -- November 16th

Create material list/cost analysis: Bill of materials -- November 23rd

Complete Poster: Turn in poster -- November 23rd

Complete Final Design Package: Turn in design package files -- December 7th

Spring 2019

Milestone: Deliverable -- Due Date

Order all Parts and Materials: Submit PO's and/or Receipts -- February 1st

Built Prototype: Images of completed design -- March 1st

Testing Procedure: Testing Plan and Procedure with a goal of drying 8 bushels in 8 hours -- March 8th

Bill of Materials and Drawings: Updated BOM and As-Builts CAD files -- March 29th

Complete Testing: Summary of Results including graph of moisture content over time -- April 12th

Complete Poster: Turn in poster -- April 19th

Written Report: Engineering Design Report -- April 26th

Website Completed: Submit website url -- April 26th

Complete Final Design Package: Turn in design package files -- April 26th