1203 S. Clark Road Cedar Hill, Texas 75104
Architects: Huckabee & Associates
Construction Manager at Risk: CORE Construction
Bond Project Manager: Dikita Enterprises
Playground Vendor: LEA Park and Play
Design Begins: April 2025
Construction Begins: June 2026
Expected Duration: 14 months
Upgrade Safety & Security: new secure vestibules with access control, install fencing around playgrounds, new cameras throughout campus, new public address, bells, and clocks, and safety glazing film
Upgrade Technology Infrastructure: devices for students and teachers, interactive whiteboards, and document cameras
Furniture and equipment; update stage lighting and sound
Roof and HVAC Upgrades (work to be performed on the 2001 addition only), fire sprinklers installed
Interior Improvements for NEW Biomedical Science classrooms, restrooms, flooring, ceiling tile repairs, painting, and cabinets installed
2 new ADA-accessible playgrounds