1203 S. Clark Road Cedar Hill, Texas 75104
Architects: Huckabee & Associates
Construction Manager at Risk: CORE Construction
Bond Project Manager: Dikita Enterprises
Playground Vendor: LEA Park and Play
Design Begins: April 2025
Construction Begins: June 2026
Expected Duration: 12 months
Upgrade Safety & Security: bullet-resistant glass & frames, playground fencing, new cameras, update public address system
Upgrade Technology Infrastructure: devices for students and teachers, interactive whiteboards and document cameras
Furniture and equipment; update stage lighting and sound
Roof and HVAC Upgrades (work to be performed on the 2001 addition only), fire sprinklers installed
Interior Improvements for NEW Biomedical Science Lab Interior renovations including restrooms, flooring, ceiling tile repairs, painting, and cabinets installed
2 new ADA-accessible playgrounds
Construction is set to begin on new playgrounds at all six Cedar Hill ISD elementary campuses, bringing exciting new play experiences for scholars. The decision was made to start construction and installation of playgrounds at once, despite where a campus project lands on the timeline.
To ensure these playgrounds meet the needs and interests of our scholars, student feedback sessions were held at Collegiate Prep Elementary and Waterford Oaks Elementary. Scholars shared their ideas and helped shape the playground designs.
Each playground will accommodate 50 to 62 children at one time and feature: Inclusive spinners Inclusive swing sets Therapeutic disc swings
Playground Construction Schedule
May 26: Lake Ridge & High Pointe
June 2: Plummer
June 9: Waterford Oaks
June 23: Highlands
July 7: Collegiate Prep