1208 E. Pleasant Run Rd Cedar Hill, Texas 75104
Architects: Huckabee & Associates
Construction Manager at Risk: CORE Construction
Construction Project Manager: Dikita Enterprises
Design Begins: January 2026
Construction Begins: January 2027
Expected Duration: 16 months
Upgrade Safety & Security: new secure vestibules with access control, new cameras throughout campus, new public address, bells, and clocks, and safety glazing film
Upgrade Technology Infrastructure: interactive whiteboards and document cameras, devices for students & teachers
Install walkways to Waterford Oaks Elementary School (Bessie Coleman MS Trail)
Furniture and equipment
Update campus boilers, repair campus elevator, install vape detectors in restrooms, HVAC and roof upgrades, and fire sprinklers installed
Interior improvements for Fine Arts Program (black box theatre, art, orchestra, dance), stage lighting, and sound, fire sprinklers installed
Interior renovations, including restrooms, flooring, ceiling tile repairs, painting, and cabinets installed