Together, We're Building!
Renovated Classroom
Renovated Classroom
Renovated Library
Bond Program Update – October 2026
Cedar Hill ISD’s 2024 Bond Program continues to make progress toward creating safe, modern, and innovative learning environments for scholars, staff, and the community. From campus renovations and facility improvements to transportation and technology upgrades, these investments are helping prepare our district for the future.
Proposition A: Construction
High Pointe Elementary Fine Arts Academy – Construction was completed in Summer 2026 and all new furniture and equipment were delivered and installed in time for the start of the 2026–2027 school year. The Bond Team is now working with the Architect and Contractor to complete the project’s final closeout process.
L. Kim Lewis Auxiliary Services Center/Transportation Facility – The design team has completed the 100% Construction Documents. All design disciplines have reviewed the drawings in coordination with District staff to ensure the project is fully integrated and ready for the next phase. The project will proceed to bidding, with construction scheduled to begin following completion of the bidding process and award of the construction contract.
Lacy Enrollment Center – Phase 1 construction is complete. STRIVE and Hilltop have moved into the Enrollment Center and began the 2026–2027 school year in their new location. Phase 2 construction is progressing as the contractor continues work on the Student Enrollment, Police Department and Shift 18+ spaces.
Waterford Oaks Elementary School – Renovation work began in June 2026, starting with the removal of existing ceilings, building systems, and finishes. Construction is progressing across all areas, with framing and in-wall installations nearing completion. Wall finishing and roofing are underway.
During construction, Waterford Oaks Elementary scholars and staff are temporarily relocated to the JoLynn Maddox Teaching and Learning Center (TLC). This arrangement provides the contractor with full access to the Waterford Oaks campus and allows work to proceed efficiently. The project is expected to be completed in July 2027.
New furniture will be ordered and installed before the start of the 2027–2028 school year, ensuring that scholars and staff return to refreshed, fully equipped learning spaces.
Plummer Elementary School – Renovation is progressing through multiple phases to improve learning spaces and campus facilities.
Phase 1, which included classroom renovations, was completed in Summer 2026 and new furniture was installed.
Phase 2, which includes additional classrooms, is progressing ahead of schedule and is scheduled for completion in December 2026.
Phase 3 will include the Library and Health Sciences classrooms, with construction scheduled to begin during the Winter Break 2026.
Phase 4 will encompass the Administrative offices, Cafeteria, and Gymnasium, with completion scheduled for Summer 2027.
New furniture and equipment for Phases 2–4 will be ordered and installed before the start of the 2027–2028 school year.
Cedar Hill High School – Design work began in October 2025 to plan comprehensive building upgrades that will enhance campus safety, functionality, and the learning environment. Planned improvements include new elevators; water heater replacements; roof and HVAC upgrades; gymnasium improvements, including new bleachers; enhancements to the Performing Arts Center; classroom renovations; updated flooring, painting, and cabinetry; new furniture and equipment; and additional security enhancements.
The design team is completing the 100% Construction Documents, with all design disciplines reviewing the plans alongside District staff to ensure coordination across the project. Bidding will follow and construction is expected to begin after the bidding process is completed and the construction contract is awarded.
Bessie Coleman Middle School – Design work began in January 2026 to identify improvements that will modernize the campus and enhance safety, building performance and instructional spaces.
Proposition A: Non- Construction
Technology Upgrades
As part of the 2024 Bond Program, Cedar Hill ISD is investing in technology to strengthen infrastructure, enhance cybersecurity, and support engaging, future-ready classrooms.
Proposition A includes improvements to the District’s technology infrastructure, including expanded network capacity, increased internet speeds, enhanced cybersecurity, and upgrades to classroom technology. These investments support reliable connectivity and the effective use of instructional technology across campuses.
Transportation Fleet Improvements
Cedar Hill ISD continues to invest in transportation to support the needs of its scholars. Seven buses were purchased in Fall 2025 and delivered in January 2026, including three 54-passenger buses and four 77-passenger buses.
An additional 10 buses were purchased in May 2026, including three 54-passenger Special Education (SPED) buses and seven 77-passenger buses. All 10 buses were received in August 2026, further strengthening the District’s transportation fleet and supporting safe, reliable student transportation.
Proposition B: Technology Devices
Technology purchases in August 2024 included interactive whiteboards, document cameras, and updated devices for students and staff. These resources help enhance classroom instruction, promote engagement, and provide scholars and educators with tools to support teaching and learning.
Together, these investments are improving technology reliability and connectivity while helping create modern, secure, and innovative learning environments throughout the District.
Investing in Our Future
Cedar Hill ISD remains committed to transparent communication, responsible stewardship of bond funds, and keeping our community informed as these projects progress. Every improvement reflects our commitment to providing safe, modern and inspiring learning environments for all scholars.
The 2024 Bond Program represents more than buildings, renovations, and equipment. It is an investment in the future, opportunities and success of every scholar we serve.
To learn more about the projects, planned improvements, and scope of work at each campus included in the 2024 Bond Program, visit the District’s Proposition A and Proposition B project pages.
Together, we’re building better futures for every scholar.