November 6-8: Begin testing prototype. We will test with static weights and Beka.
November 13-15: Research and order materials from Home Depot. Work on detailed measurements and blueprints.
November 19: Sara and Mayzie pick up materials from Home Depot and begin cutting down plywood, 2x2s, and 2x4 to final size.
November 26-28: All members will help with construction. Mayzie uses a drill and screws to connect pieces while McKenna and Sara help keep pieces flush and work on sanding down 2x2s.
December 4-6: Sara and Mayzie finish construction while McKenna works on the final documentation and final presentation.
December 15: Mayzie, Sara, and McKenna meet at Sara's house to finish routing the edges (Mayzie), staining the inside (all members), and adhering the carpet (Sara and McKenna). Project will be finished by the end of the day.
December 11: Deliver final project to Ann, Beka, and Daja.