Our business continuity plan will help us survive and continue running after a major disruption or disaster like a fire or earthquake. It highlights the step-by-step process of what should be done to prevent risks that can lead to your business having to close down
In the event of a disaster which interferes with ThingLogix’s ability to conduct business from one of its offices, this plan is to be used by the responsible individuals to coordinate the business recovery of their respective areas and/or departments. The plan is designed to contain, or provide reference to, all of the information that might be needed at the time of a business recovery.
Notes:
ThingLogix staff uses Cloud based commercial software, there are no physical servers, phone systems etc. on premise. ThingLogix staff can access Business cloud services from anywhere with an internet connection.
---
Index of Acronyms: (BCP) Business Continuity Plan
Section I, Introduction, contains general statements about the organization of the plan. It also establishes responsibilities for the testing (exercising), training, and maintenance activities that are necessary to guarantee the ongoing viability of the plan.
Section II, Business Continuity Strategy, describes the strategy that the ThingLogix will control/implement to maintain business continuity in the event disruption. These decisions determine the content of the action plans, and if they change at any time, the plans should be changed accordingly.
Section III, Recovery Teams, lists theRecovery Team functions, those individuals who are assigned specific responsibilities, and procedures on how each of the team members is to be notified.
Section IV, Team Procedures, determines what activities and tasks are to be taken, in what order, and by whom in order to affect the recovery.
Section V, Appendices, contains all of the other information needed to carry out the plan. Other sections refer the reader to one or more Appendices to locate the information needed to carry out the Team Procedures steps.
The objective of the Business Continuity Plan is to coordinate recovery of critical business functions in managing and supporting the business recovery in the event of office building disruption or disaster. This can include short or long-term disasters or other disruptions, such as explosions, terrorism, extended power interruptions, hazardous chemical spills, and other natural or man-made disasters.
A disaster is defined as any event that renders a business facility inoperable or unusable so that it interferes with the organization’s ability to deliver essential business services.
The priorities in a disaster situation are to:
The Business Continuity Plan is limited in scope to recovery and business continuance from a serious disruption in activities due to non-availability of ThingLogix’s facilities. The Business Continuity Plan includes procedures for all phases of recovery as defined in the Business Continuity Strategy of this document. Unless otherwise modified, this plan does not address temporary interruptions of duration less than the time frames determined to be critical to business operations.
The scope of this plan is focused on localized disasters such as fires, floods, and other localized natural or man-made disasters. This plan is not intended to cover major regional or national disasters such as regional earthquakes, war, or nuclear holocaust. However, it can provide some guidance in the event of such a large scale disaster.
The viability of this Business Continuity Plan is based on the following assumptions:
Maintenance of theBusiness Continuity Plan is the joint responsibility of the ThingLogix Executive Team.
ThingLogix Executive Team is responsible for ensuring the workability of their Business Continuity Plan. This should be periodically verified by passive testing - once a year.
In the event of a disaster or disruption to the office facilities, the strategy is to recover operations by relocating to an alternate business site. The short-term strategies (for disruptions lasting two weeks or less), which have been selected, include:
Primary Location
ThingLogix, Inc. 1301 Shoreway Rd, Suite 280, Belmont CA 94002
Alternate Business Site
Suggestions are to use one of the many temporary workspace rental services available nearby. There are multiple options, so choosing the first one that meets the financial criteria, space requirements, and locality shall be expected.
The activities necessary to recover from a ThingLogix facilities disaster or disruption will be divided into four phases. These phases will follow each other sequentially in time.
This phase begins with the occurrence of the disaster event and continues until a decision is made to activate the recovery plans. The major activities that take place in this phase includes: emergency response measures, notification of management, damage assessment activities, and declaration of the disaster.
In this phase, the Business Continuity Plans are put into effect. This phase continues until the alternate facility is occupied, critical business functions reestablished, and computer system service restored to ThingLogix’s Departments. The major activities in this phase include: notification and assembly of the recovery teams, implementation of interim procedures, and relocation to the secondary facility/backup site, and re-establishment of data communications.
This phase begins after secondary facility operations are established and continues until the primary facility is restored. The primary recovery activities during this phase are backlog reduction and alternate facility processing procedures.
This phase consists of any and all activities necessary to make the transition back to a primary facility location.
No critical records, which would have to be reconstructed are kept physically onsite. All critical records must be available online.
The following categories of information can be exposed to loss:
1. Any files stored on-site in file cabinets and control file rooms. (None on site)
2. Information stored on local PC hard drives. (None on site; all PC/laptops should be taken home with employees each night)
3. Received and un-opened mail.
4. Documents in offices, work cubes and files.
In the event of a facilities disruption to our offices, ALL users should be assisted in re-establishing connectivity to Internet through home, wireless hotspot or alternate means.
During the time that ThingLogix department operates from the secondary facilities, USPS will be notified of change of address.
This section lists the staff gives a short explanation of the function
<Department Name> Recovery Team:
Responsible for oversight of the <Department Name>recovery functions.
This section identifies the team roles and the specific responsibilities that have been assigned to the team.
Team leader - Overall coordination (Carl Krupitzer, CEO)
Backup Team Leader - Overall coordination (Nilesh Patel, Delivery Lead)
Team members are to be notified if the plan is to be put into effect, Carl or the Operations Manager will email and phone staff.
ALL Key Staff and Business Contacts Telephone Lists
(Operations Manager to maintain and release also shared with Nilesh). Note: Alternatives for communication via email, messaging, or phone is also stored within GSuite, Slack and within Quickbooks.
Other people might need to be contacted during the recovery process. Their names and telephone numbers are provided.
In the event of a disaster, the Business Continuity Coordinator is responsible for ensuring that the following activities are successfully completed:
This team is responsible for providing information regarding the disaster and recovery efforts to:
· Senior Management
· Customers
· Vendors/Contracts
· Other Stakeholders
This team is responsible for:
This team member is responsible for:
ACTIVITY IS PERFORMED AT LOCATION: Main Office
ACTIVITY IS THE RESPONSIBILITY OF THIS TEAM: All Employees
TASKS:
1. After a disaster occurs, quickly assess the situation to determine whether to immediately evacuate the building or not, depending upon the nature of the disaster, the extent of damage, and the potential for additional danger.
Note: If the main office is total loss, not accessible or suitable for occupancy, the remaining activities can be performed from alternative emergency site after ensuring that all remaining tasks in each activity have been addressed. This applies to all activities where the Main Office is the location impacted by the disaster. The emergency site may be temporarily setup at any one of several optional locations, depending on the situation and accessibility of each one.
2. Quickly assess whether any personnel in your surrounding area are injured and need medical attention. If you are able to assist them without causing further injury to them or without putting yourself in further danger, then provide what assistance you can and also call for help. If further danger is imminent, then immediately evacuate the building.
3. If appropriate, evacuate the building in accordance with your building’s emergency evacuation procedures. Use the nearest stairwells. Do not use elevators.
4. Follow building Facilities instructions for meeting point outside the building.
5. Do a roll call to ensure that all employees are accounted for.
ACTIVITY IS PERFORMED AT LOCATION: At Any Available Phone
ACTIVITY IS THE RESPONSIBILITY OF: Any member of staff
PRIMARY: Carl
ALTERNATE: Nilesh
TASKS:
1. Team leader informs the Leadership team and all staff.
3. Depending upon the time of the disaster, personnel are instructed what to do (i.e. stay at home and wait to be notified again, etc.)
ACTIVITY: Preliminary Damage Assessment
ACTIVITY IS PERFORMED AT LOCATION: Main Office Location
ACTIVITY IS THE RESPONSIBILITY OF: Any member of staff
TASKS:
1. Contact the Carl or Nilesh to determine responsibilities and tasks to be performed
ACTIVITY: Notification to Employees
ACTIVITY IS PERFORMED AT LOCATION: Alternate Site
ACTIVITY IS THE RESPONSIBILITY OF: Carl or Nilesh
TASKS:
ACTIVITY: Alternate Site Processing Procedures
ACTIVITY IS PERFORMED AT LOCATION: Alternate Site
ACTIVITY IS THE RESPONSIBILITY OF: All Employees
TASKS: