7.1. To unite the testing plan, preparing works and coordination between testing units with the establishment using equipment.
7.2. Inspection of technical dossiers:
Dossiers for inspection have at least:
- Equipment history, technical records of equipment (for repair, renovation equipment required to have further records of design, renovation and repair), the certificates of cable, hooks, parts, safety parts assemblies.
- Installing dossiers (for fix installed equipments), repair and renovation of equipment.
- Dossiers on result to measure the equipment safety parameters, related systems: ground system, lightning-resistance systems, electrical systems and other protection systems.
- Dossiers on use management, operation, maintenance and results of the previous testings (if any).
- The results of the inspection, examination and implementation of the recommendations of the previous inspections, examinations and testings (if any).
7.3. Fully prepare the devices and facilities to determine the safe technical specifications for the testing process.
7.4. To ensure adequate means, testing load, personal protective equipment and process, safety measures during the course of testing.