Design Plans for a new Pollard
In December 2025, The Pollard School Building Committee (SBC) voted to move forward with designing a new grade 6-8 school at the current Pollard site on Harris Avenue. The new building design is driven by the educational program for grades 6-8, with spaces designed and sized to meet the needs of the existing middle school curriculum.
The new school will be built in two phases. During Phase 1, grades 7 and 8 will continue to use the existing school while the new building is constructed behind the existing Pollard building. Once Phase 1 is complete, students will move into the new school, the existing Pollard building will be demolished, and Phase 2 will begin with construction of the new 6th-grade wing. This approach allows for a lower overall building height and a dedicated 6th-grade wing.
Existing Pollard Building Footprint
New Pollard Building Footprint
Overhead View
Phase 1 construction will consist of the main hub of the building and two classroom wings for grades 7 and 8 to the rear. Phase 2 will construct a two and three-story grade 6 wing towards Harris Avenue.
The Pollard site is highest at the north end near Harris Avenue, and slopes down at the south end near the commuter rail tracks. The new building design takes advantage of the grade change: two- and three-story sections will be built into the slope, creating a total of four levels across the entire school.
Front (North) Elevation
When viewed from Harris Avenue, the building will appear one to two stories tall. This will be the main entrance to the school, and is located on the third level of the building.
Overall, the tallest part of the building will be the top floor of the 6th grade wing, located to the right of the main entrance.
Cross Section (from west)
There is a 30-foot grade change from the front entrance of the building (left) to the rear (right).
Side (West) Elevation
A second entrance will be located on the west side of the school on the first level. This is where buses will drop off and pick up students.
Rear (South) Elevation
As seen from the commuter rail tracks, the building will appear three stories tall. The third floor will be set back, providing useable outdoor spaces on the roof of the building.
The building is designed around a central core or hub that contains school administration and common areas such as the cafeteria, library, gymnasium, and spaces for art, music, and other enrichments. Three classroom wings surround this core: one for 6th grade, and two for 7th and 8th grades. The grade wings include academic and special education classrooms as well as centrally located collaboration space.
First Level
Second Level
Third Level
Fourth Level
Both High Rock and Pollard currently lack sufficient space. By today's standards, most of the classrooms are undersized, as well as common areas such as the libraries, gyms, cafeterias, and performance spaces. The areas will be right-sized to meet the needs of the curriculum, and designed to be flexible and multi-use.
Cafeteria
Existing: 6,200 sf / 4 lunch periods
Future design: 10,013 sf / 3 lunch blocks
Library
Existing: 3,250 sf
Future design: 5,050 sf
Classrooms
Existing (average): 775 sf
Future design: 850 sf (per MSBA guideline)
Auditorium
Existing: 6,360 sf / 434 seats
Future design: 12,000 sf / 750 seats
Gymnasium
Existing: 10,840 sf — 2 gymnasiums
Future design: 11,100 sf — with divider curtain