IMPLEMENTATION TIMELINE
Pre-Planning Phase, July 2024 - September 2024
Introductory meetings between Summit project team members and implementation consultants; learn about methodology and process.
Project Planning / Project Start, October 2024 - December 2024
Project team members meet with consultants, share information about current processes.
Architect & Configure, January 2025 - February 2026
Consultants and project team members begin iterative process of building the MHC instance of Workday Student.
Testing & Phased Training, March 2026 - October 2026
Project team members will test business scenarios in the new system; opportunities will be available for MHC community members to volunteer in the testing process. Training materials and sessions will be developed and offered to prepare the community.
Move to Production, November 2026 - September 2027
New system will be live in production; various functions will start being utilized by faculty, staff and students during the spring 2027 semester an fully in place for 2027-28 academic year. Training sessions for the community will continue to be offered through fall 2027.