Week 8 Accomplishments:
The majority of parts were received from McMaster to begin assembly of the test rig. Several adjustments had to be made in the assembly process as the parts didn't fit flush as well in the CAD. In the end after grinding and bending, the test rig c-channels fit well and were ready to be sealed for pressure tests. CAD to mount the latch style clamps was also accomplished.
Goals for Next Week (list names after each item). Due by sponsor meeting on Wednesdays.
Finish assembly of the test rig platform and permanent fixture at the bottom - Anyone/Everyone
Begin setup of the test rig platform for testing.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
In Person (via Microsoft Teams):
Great progress and our sponsors our excited to see our future test results.
Sponsors inquired about a final presentation and how the scheduling would be.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
In person (via zoom):
No updates on obtaining an ANSYS engineer to help us with the setup of an FEA simulation.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
After grinding down parts and making manual adjustments, how confident will we be that we can seal it properly to give an accurate result for our pressure tests.
Resources or Information Required but not Available
N/A
Schedule
Refer to the Gantt Chart
Budget (list amount spent and amount remaining)
spent: $1035.27
remaining: $764.73