Overview of Status of Analysis, Design, Fabrication, Tests, etc.
We defined the risk reduction test and tried to start it this week.
Accomplishments from Previous Week
defined the risk reduction test
listed the components for test
Goals for Next Week (list names after each item). Use specific and measurable objectives.
set up the risk reduction test
evaluate the feasibility of cooling method used in the test
prepare the presentation
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Risks and Areas of Concern
the efficiency of the cooling method
the time required to cool down to desired temperature
the heat generated during cooling
Schedule
Monday 12/2/19, 10:00a: meeting with StevesÂ
Monday 12/2/19, 4:00p: meeting with sponsor
Wednesday 12/4/19, 15:00p: meet with Gravish
Budget (list amount spent and amount remaining)
$92.32 Spent
$2907 Remaining
Progress on Report and Webpage