Overview of Status of Analysis, Design, Fabrication, Tests, etc.
N/A
Accomplishments from Previous Week
Emailed sponsor to begin setting up a time to have our first meeting.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Meet with project sponsor and Dr. Delson.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Unable to meet with sponsor this week.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Ask sponsor for references to prepare for first meeting with the sponsor.
Emailed sponsor.
Received a research article discussing tendon transfer limitations.
Risks and Areas of Concern
N/A due to being unable to meet with sponsor.
Resources or Information Required but not Available
Resources from sponsor that will be provided in the future
Schedule
Meet with sponsor 12/3/12
Meet with Dr. Delson 12/4/12
Budget (list amount spent and amount remaining)
Total Budget: $7,000
Nothing has been spent
Progress on Report and Webpage