Overview of Status of Analysis, Design, Fabrication, Tests, etc.
N/A
Accomplishments from Previous Week
Met with Dr. Delson and received documents from sponsor to prepare for presentation.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Sensitivity analysis of current tendon data
New design ideas
Complete presentation
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor asked for 5 ideas from each member of the group. 25 ideas total. Called "Dreaming" phase.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Gain a better understanding of strain gauge technology.
Get reference on strain gauges.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
No finalized design yet, but that is what the sponsor wants.
Resources or Information Required but not Available
Still looking for resource specific to load cells.
Schedule
See gantt chart
Budget (list amount spent and amount remaining)
$7000, and not a dime has been spent yet
Progress on Report and Webpage