Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Decided to purchase AC motor to begin tests on measuring wind speed
Began learning Pro/E to start designing the new Wind-Clik
Accomplishments from Previous Week
Met with Isaiah, and found that there weren't any old AC motors in the component room
Reverse Engineered a part given to us by Hunter using Pro/E
Researched buying AC motors
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Work on and complete Design Proposal Presentation due next Tuesday - Team Effort
Purchase an AC motor and begin testing process - Eric Kenyon
Complete Meeting Minutes/Weekly Status email to Sponsor - Eric Abraham
Manage and further add detail to website - Isaac Kim
Begin design of prototype in Pro/E - Anthony Chong, and others as this will be a group effort
Decide other materials which need to be ordered now to begin testing AC motor - Isaac Kim
Complete Progress Report and begin looking into first draft of project report - Eric Abraham
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Create an even further refined schedule/Gantt chart using Microsoft Project
Action = Meeting Tuesday (today) to work on the schedule before meeting with Hunter
Reverse engineer a part using Pro/E
Action = Used calipers to find dimensions of part, and members spent time on own using Pro/E to design/assemble
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Include names for delegation of tasks to be completed by next week
Names were included to show which specific items team members are working on
Go into more detail about risks/areas of concern on Progress Report
More detail added to clarify risks/concerns
Avoid building AC motor for concept
Research done to decide on where to obtain an AC motor
Risks and Areas of Concern
Nothing of great concern
Possibly... can we design an anemometer(wind cups) on our own in Pro/E since we will not be given one yet
Possibly purchase an anemometer to test?
Resources or Information Required but not Available
Isaiah Freersken - showed us the component room
(clarify this section of progress report??)
Schedule
Begin designing Wind-Clik in Pro/E for Design Proposal Presentations next Week
Purchase AC Motor
Budget (list amount spent and amount remaining)
Nothing spent yet; however purchases will begin this week
Progress on Report and Webpage
Webpage is moving forward well - Isaac Kim is adding more information as we go, and group members are uploading useful documents