Overview of Status of Analysis, Design, Fabrication, Tests, etc.
determined general plan for the robot design
conducting research in every aspect of the project to determine best path
Accomplishments from Previous Week
Meetings with Sponsor
Introduced to potential work area
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Begin purchasing parts
Have a full access badge
Write Individual Component Analysis for determining what we will need to purchase
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
We set up a meeting for 3:30pm on Thurs 1/12 with Goodrich and set up weekly meeting time (Tues at 3pm)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Set a reasonable scope so that Goodrich will not be mad if we cannot achieve all their goals, so we set up a meeting with our sponsor
Risks and Areas of Concern
Budget and Scope of Project
Resources or Information Required but not Available
What model of paint sprayer Goodrich uses
Schedule
Describe upcoming milestone
Get website up and running
Finish Individual Component Analysis
Update Gantt chart.
Budget (list amount spent and amount remaining)
zero spent
Progress on Report and Webpage
updated progress report
need to add in other information