Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Ball Mount is in 3D print queue
Making drawings for every concept that is an option/drawings will be clearly defined
FBD for movement of top plate
Need analysis for load on slider plate (need help)
thread load analysis (currently use
Accomplishments from Previous Week
Cone Proto-type has been 3D printed
Slider has been 3D printed
Asked for ProductView package
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Have completed drawings
Implement every mounting design into package
Complete the test bed...therefore may need to make 3 more machined bosses in order to complete the set
Get sponsor direction for development need of concept proposals
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
ProductView package is being put together
"Pack and go" package will allow us to see all components on frame
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Possibly use floating nut 5/8/2012
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
use some sealant to protect the threads
there is a metal work shop on campus in “campus services complex” and someone there should have expertise on what you are looking for
for testing the load, consider using the materials testing device in EBU2 lab
Risks and Areas of Concern
Vibration from turbine might cause the screws to come loose- Loctite was suggested by sponsor
Fluid buildup in our plate designs
Corrosion resistant threads a possibility?
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Budget remaining: $579
Progress on Report and Webpage
Website is up to date
Peer Feedback from last week needs to be uploaded
More pictures need to be uploaded (perhaps from ProductView)