TCJ3C Agenda
Agenda - Fall Course
Week 1
Tuesday- Introductions, what this class is about / Course Outline, rules/expectations, careers in construction, why construction -
Small hands on activity or Imperial Measurement / Fractions
Wednesday - Google classroom, Imperial measurement , wood frame construction assignment on google classroom due Friday
Thursday - Mr McMillan away - video on Burj Khalifa construction , continue on Wood Frame Construction assignment
Friday - platform framing, passive haus , Finish wood frame construction assignment on google classroom
Week 2
Monday - Lumber dimensions, Plot plan, Start safety instruction, demonstrations & Edpuzzle videos on google classroom
Shop safety site , General shop safety , Mitersaw safety
Tuesday- Miter Saw demonstrations - Circular saw safety presentation , Plot plans
Wednesday - headsup electrical safety , portable tool safety , sections & Elevations worksheet
Thursday - Continue with Circular saw demos & sign offs on equipment, Seatwork - floor plan sheet, Edpuzzle videos, Heads-up sheet
Friday - Finish floor plan sheet, Edpuzzle videos, Heads-up sheet - Skills passport demos & sign offs on equipment - Test review for Monday
Week 3
Mon - Mr McMillan away - Safety Test - Wall section with Mr May
Tuesday - Continue wall section in google sketchup - All Edpuzzle videos should be complete - All Sign-offs on tools should be complete
Wednesday - procedures for working outside - introduction to construction site
Thursday - procedures for working outside - introduction to construction site
Friday - First day of building outside
Week 4
Mon - Finish 3,4,5, squaring up checking diagonals, Practice 16 inch on center layout. fix saw horses
Tuesday - Each student will lay out a 16 inch on center stud - group work to build saw horses
Wednesday - Continue building Sawhorses
Thursday - Begin Building sheds
Friday - Continue building sheds
Week 5
Mon - Continue building outside
Tuesday - Continue Building outside
Wednesday - Review video of 16" on center layout, Finding the midpoint - jacks, cripples, kings, sill, headers, and wall layout
Thursday - Wall layout activity - How to lay out a plate with windows / doors maintaining 16" on center
Friday - Advanced Framing Video , This old House NET ZERO , Continue building outside
Week 6
Mon - Speed square demo, types of roofs (began), rafter parts - building outside
Tuesday - Building outside
Wednesday - Mr McMillan was sick - Test - Sketchup
Thursday - Mr McMillan was sick - This old House - Sketchup
Friday - PD Day
Week 7
Mon - Easter Monday
Tuesday - Building outside
Wednesday - Building Outside (finish writing test in missed test room)
Thursday - Foundations / Half period outside
Friday - Foundations & Ice damming
Week 8
Mon - Building outside
Tuesday - Rain - Take up Test 1 - Layout exercise - Add to sketchup model
Wednesday - Building outside
Thursday - Building outside
Friday -
Week 9
Mon - Outside Building
Tuesday - Framing square for stairs and rafters - Outside building
Wednesday - Safety review / conversation - Outside building
Thursday - Rain day - google sketchup - modify foundations to reflect to acquisitions, weeping tile, j-bolt, etc.
Friday - Very windy day - depending on afternoon weather - either Sketchup or building outside
Week 10
Mon - build outside all week
Tuesday - finish wall sections
Wednesday - siding wall sections
Thursday - siding wall sections
Friday - siding wall sections
Week 11
Mon - finish walls
Tuesday - snow day
Wednesday - rafters ( in shop) - similar triangles & cosign
Thursday - rafters (in shop) - similar triangles & cosign
Friday - PD day
Week 12
Mon - Rafters cont'd - similar triangles & cosign
Tuesday - Rafters Cont'd
Wednesday - Rafters cont'd
Thursday - Finish all rafters on all sheds
Friday - cutting sheathing for roofs
Week 13 -
Mon - Prepping for assembly of roof
Tuesday - Finish cutting sheathing for roof
Wednesday - Prepping gable end blocking & roof sheathing
Thursday - In-school field trip - assemble the entire roof
Friday - Finish small details on the roof - blocking for gable end studs, sheathing for gable ends
Week 14 -
Mon - finish gable end sheathing, fishing blocking for gable ends - continue working on small sheds - sheath roofs, install siding
Tuesday - Finish small sheds
Wednesday -
Thursday - Finish small sheds
Friday - PA day - no school
Week 15 -
Mon - Cut sheathing for roofs, begin installing drip edge
Tuesday - continue installing, drip edge & felt, lay out shingles using chalk line
Wednesday - finish shingling roof
Thursday - finish shingling roof, cut doors and install doors
Friday - finish up small sheds
Week 16 -
Mon - Shingling roofs
Tuesday - Shingling roofs
Wednesday - Prep for rafter summative
Thursday - Rafter summative
Friday - finish Rafter summative - finish shingling roofs
Week 17 - Jan 6 - 10
Mon - Start Electrical
Tuesday - Electrical
Wednesday - Prep for wall summative
Thursday - Wall Summative
Friday - Electrical
Week 18 - Jan 13 - 17
Mon - Electrical circuits
Tuesday - Electrical circuits
Wednesday - Electrical circuits
Thursday - Electrical Summative
Friday - Electrical Summative
Week 19 - Jan 20 - 24
Mon - Electrical Summative
Tuesday - Electrical Summative
Wednesday - Electrical Summative
Thursday - Electrical Summative Due
Friday - Clean up
Agenda - Spring Course
Week 1
Monday - Introductions, what this class is about / Course Outline, careers in construction, why construction -
Small hands on activity
Tuesday - Imperial Measurement / Fractions
Wednesday - Google classroom, Imperial measurement & math for trades
Thursday - Imperial Measurement, Wood dimensions, plot plan video, plot plan ppt , passive haus
Friday - plot plan video, plot plan ppt , home building video , Foundations - foundation kahoot
Week 2
Monday -* (pushed back one day because of OYAP presentation in the caf)
passive haus home building video , Foundations - foundation kahoot
Tuesday -
Safety instruction, demonstrations & Edpuzzle videos on google classroom
Shop safety site , General shop safety , Mitersaw safety
Tuesday- Circular saw safety , cordless drill ,
Wednesday - headsup , portable tool safety , materials handling safety
Thursday - Skills passport demos & sign offs on equipment
Friday - - Skills passport demos & sign offs on equipment
Week 3
Monday - Family Day
Tuesday - Edpuzzle videos & blue print reading activity
jig saw and sawzall safety
Wednesday - Edpuzzle videos & blueprint reading activity
Thursday - Edpuzzle videos & blueprint reading activity
Friday - Take up Headsup BC safety, Safety test, blueprint reading
Week 4 - Feb 25 - Mar 1
Monday - Foundationcode.pdf & Sketchup - Please go to the google classroom and find the first three sketchup videos
Tuesday - Google sketchup continued on chromebooks.
Wednesday - Missed test room - Make up safety test if you missed it - Continue in google sketchup
Thursday - Sketchup cont'd
Friday - Last day of sketchup - hand in foundation and floor joists
Week 5 - Mar 4 - 9
Monday - Insulation & Insulation questions , R-Value video, This old house insulation video
Tuesday - Insulation cont'd - option to add -
Questions and link will be submitted on the google classroom.
http://www.nrcan.gc.ca/sites/www.nrcan.gc.ca/files/energy/pdf/housing/Chapter2_e.pdf
Questions below :
https://docs.google.com/document/d/1QegCakx-ffYv9gjEl8QcMQd25i1jh0LyiN77tKC908g/edit
Wednesday - Unit test
Electrical site & Electrical slideshow to complete these electrical questions
Thursday - If paper work is complete, begin electrical on the electrical site
Friday - Electrical - Presentation by Electrical Engineer Graeme Davidson - cont - residential wiring
March Break
Week 6
Mon - Wiring Electrical boxes
Tuesday - continue electrical wiring
Wednesday - Wiring electrical circuits
Thursday - Cont with Electrical
Friday - Electrical Work continued -
Week 7 -
March 25-March 29
Mon - Last day for wiring Electrical boxes
Tuesday - Begin Electrical Summative
Wednesday - Continue with Electrical Summative
Thursday - Electrical Summative Continued
Friday - Electrical test & continue with Electrical Summative
Week 8
April 1st - April 5th
Mon - Order arriving from Rona, explanation of construction site, organizing materials, marking crown etc.
Tuesday - Finish up Electrical Summative
Wednesday - Set up construction site & begin building sheds
Thursday - Build 16" on center base for shed and three small 16" On center bases for recycling container
Friday - Continue building the bases - make sure they are square by checking diagonals and then screw plywood onto the base - one screw every 6" around the perimeter and one screw every 12" across the middle of the joists.
Week 9
April 8th - April 12th
Mon - Finish Floor framing
Tuesday - Begin Framing Walls for all structures
Wednesday - Continue Framing Walls
Thursday - Continue Framing Walls
Friday - PD Day - No school today
Week 10
Mon - Cont framing walls
Tuesday - Continue Framing Walls
Wednesday - Continue Framing Walls
Thursday - Continue Framing Walls
Friday - Holiday - no school
Week 11
April 22-26
Mon - Holiday - no school
Tuesday - Continue Framing Walls
Wednesday - Continue Framing Walls
Thursday - Continue building sheds outside
Friday - Continue Building
Agenda - Fall Course
Week 1
Monday - Introductions, what this class is about / Course Outline, careers in construction, why construction -
Small hands on activity
Tuesday - Imperial Measurement / Fractions
Wednesday - Google classroom, Imperial measurement & math for trades
Thursday - Imperial Measurement, Wood dimensions, plot plan video, plot plan ppt , passive haus
Friday - plot plan video, plot plan ppt , home building video , Overview of a house.
Week 2
Monday - Safety instruction, demonstrations & Edpuzzle videos on google classroom
Shop safety site , General shop safety , Mitersaw safety
Tuesday- Circular saw safety , cordless drill ,
Wednesday - headsup , portable tool safety , materials handling safety
Thursday - Skills passport demos & sign offs on equipment
Friday - Group Activity - order of events in a build
- Skills passport demos & sign offs on equipment
Week 3
Monday - Types of roofs, foundation, floor, wall parts cont'd. Google sketchup lesson.
Tuesday - Sketchup builds continued.
We will use the foundation code and wall framing code and nailing schedule at the bottom of this page.
jig saw and sawzall safety
Wednesday - Sketchup & Safety continued.
Thursday - Sketchup & Safety continued. Please see google classroom for links to videos.
Friday - Sketchup & Safety continued. Please see google classroom for links to videos.
Week 4
Monday - Foundationcode.pdf & Sketchup Cont'd
Tuesday - Safety test
Wednesday Sketchup Cont'd
Thursday - Sketchup cont'd
Friday - Last day of sketchup
Week 5
Outside building shed all week
Week 6
Outside building the shed all week
Week 7
Outside building the shed all week.
Week 8
Outside building the shed all week.
Week 9
Outside building the shed all week.
Week 10
Outside building the shed all week.
Week 11
Outside building the shed all week. Last week of building sheds
Week 12
Nov 19 - 23
Outside building the shed all week.
Week 13
Nov 26-30
Outside building the shed all week.
Week 14
Dec 3 - Dec 7
Last week to finish the sheds
Week 15
Dec 10 - 14
Mon & Tue Mr McMillan away -
Write a reflection about building the shed.
Use the Electrical site & Electrical slideshow to complete these electrical questions
Tuesday - If paper work is complete, begin electrical with Mr Leduc.
Wednesday - Electrical review, start wiring
Thursday - Electrical practice - wiring receptacles
Friday - Electrical - Presentation by Electrical Engineer Graeme Davidson - cont - residential wiring
Week 16
Dec 17-21
Mon - Continue wiring boxes
Tuesday - Short class - continue wiring receptacles
Wednesday - Guest speaker - Jon Baron from the Local 96 Carpenters Union
Thursday - Electrical Quiz
Friday - Go to missed test room if you missed the quiz - last day of electrical before the break.
Week 16
(jan 7-11)
Mon - Continue wiring boxes
Tuesday - Test circuits
Wednesday - Frame small walls and begin wiring circuits
Thursday - Continue wiring circuits inside of walls
Friday - Finish circuits inside of walls
Week 17
(jan 14-18)
Mon - Summative
Tuesday - Summative
Wednesday - Summative
Thursday - Summative
Friday - Summative
Week 1
Tuesday - Introductions, what this class is about / Course Outline, careers in construction, why construction
Wednesday - Google classroom, start imperial measurement & math for trades
Thursday - Imperial Measurement, Wood dimensions, plot plan video, plot plan ppt , passive haus
Friday - plot plan video, plot plan ppt , home building video , label parts of a wall.