All projection and boadcast equpment is shared with the rest of the campus. Please see the Shared Projection Equipment Page for house equipment. Please advance any needs with a production manager for availablity and Producer or Rental Manager for costs. Streaming and Recording are also available with limited equipment availability from our Shared Broadcast Equipment.
Standard Setup
(1) Panasonic RQ25 20,000 lm 3-Chip DLP 4K Projector
11.25' x 20' (16:9 | 275" D) Screen standard hangs mid-stage but can be moved as needed.
Control and playback setup as needed on stage or at FOH audio position. Audio feed to sound standard.
Movie Setup
(2) Panasonic RQ25 20,000 lm 3-Chip DLP 4K Projector
22.5'x40' (16:9|551" D) Screen hung mid stage as needed.
Control and playback setup as needed. Stereo Audio Feed to sound, no surround sound or center channel
IMAG Setup
(2) Panasonic PTDZ13KU 12,000 Lumen DLP
(2) 8'x14' (16:9|188” D) Screens hung as needed Left & Right of Line Array even with 2nd Tier Balcony
IMAG Screen Rigging Points
All points were measured from fire pocket
Upstage Right Screen:
DS Point - 36’ 8 1⁄2” from pocket, 47’ from center
US Point – 47’6” from pocket, 37’ 6 1⁄2” from center
Upstage Left Screen:
DS Point – 36’ 8 1⁄2” from pocket, 46’ 7” from center
US Point – 47’ 6” from pocket, 39’ 4 1⁄2” from center