156A Finals Week
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Analysis:
Design: rough CAD complete, will refine in the next two weeks
Fabrication: N/A
Tests: N/A
--> this section will be changed to reflect the changed scope of the project
Accomplishments from Previous Week
Risk Reduction presentation completed
Individual Component Analyses of the arm, safety enclosure, shaft assembly, bearings, and motor have been completed
rough CAD of the entire arm/shaft/motor coupling setup has been completed
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Pending information on campus closures, etc.
Resources or Information Required but not Available
Machining resources on campus are no longer available due to the COVID-19 pandemic.
Schedule
Describe upcoming milestone
Give Risk Reduction presentation
Update Gantt chart.
Budget (list amount spent and amount remaining)
N/A
Progress on Report and Webpage
N/A