Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Assembly updated with additional 80/20 bar for support, acrylic and rubber/plastic covers for safety
Constant force spring and housing added to armrest assembly
Accomplishments from Previous Week
Parts for upper assembly structure ordered
COTS Sheet updated
Website updated to Draft 1 requirements
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish purchasing parts
Build physical chair prototype
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
5/6:
Order everything ASAP and begin building
Create complete BOM
*See "5/6 Sponsor and Delson Meeting"*
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
5/6 (Delson/Steve):
Check in with companies to ensure parts are ordered and shipping
Look into guides for designing for kids
Add support to back of backrest mechanism -> added to assembly
Look into adding constant force spring or pneumatic piston to support armrest -> added constant force spring to assembly with housing
Look into adding dampening on forward motion of backrest, similar to boom mics
Work on updating website to draft 1 requirements
*See "5/6 Sponsor and Delson Meeting"*
5/11 (Ian):
Wood is probably fine for panel and arm desk
Satisfied with 4-bar linkage for backrest adjustment
Look into working with Chris Cassidy for 3d printing
Printer can print in nylon and is more accurate
Concerns about footrest brackets
Unsure about attachment
Doesn't recommend 3d printing threads, use inserts melted into 3d printed material (contact Chris for more information)
Look into doing analysis on table to check for flexing
*See "Meeting w/ Ian 5/11/2020"*
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
none
Risks and Areas of Concern
safety
reliability
efficiency
CAD of office chair components
assembly
part ordering
Resources or Information Required but not Available
CAD/dimensions of office chair components
Tools for fabricating parts
Schedule
Week 7:
Work on fabrication/assembly
Order parts/tools
Create assembly instructions (if necessary)
Update Gantt chart.
Budget (list amount spent and amount remaining)
$215.87 spent (main frame assembly parts)
$2252.65 remaining
Progress on Report and Webpage
Webpage updated