Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Component analysis completed, prototyping process under consideration
Accomplishments from Previous Week
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Communicate with the Sponsor in regard to the project going remote.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
3/11
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
3/12 - Design presented to Delson. received good feedback in regard to the wide range of design choice considered
Suggested buying an existing RC car as a preliminary test.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Prototyping capability for the team in the future.
Resources or Information Required but not Available
Accessibility to manufacturing space
Schedule
Pick up parts from CSE building to move in to a new accessible location
Budget (list amount spent and amount remaining)
$0 spend
$2600 remaining
Progress on Report and Webpage
Finished up risk reduction presentation
Prepare for next quarter's prototype and design process