Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finalize manufacture of different part
Explore options to include fluorescent microscope with the design
Accomplishments from Previous Week
[Jing] Finalized revolving door design and manufacture G-code
[WooJae] Order camera for microscope and water level sensor for GFP recognition part
[Everyone] Made our system
[Everyone] made the presentation
Goals for Next Week (list names after each item). Use specific and measurable objectives.
[Everyone] debug system, test flow with complete planned parts
[WooJae] integrate system with water level sensor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
2/24/20 email with Jaeson (grad student)
We'll have regular pupae sample for this week and on March 10.
Genetically modified pupae will be ready by March 17 (Finals Week)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
2/20/2020 In person
Concerned about the color detection process
may need to do "computer vision" using pixel array of the photo from the UV microscope
UV microscope has a focused and intense enough UV light wave to
mount a camera to the top of the UV microscope
be able to process images
most likely moving forward with computer vision on the microscope
Concerned about which gender produces the color
Currently: first generation, both genders produce color
in the future, further generations will only have one of the genders produce color
Concerned about "re-inventing the wheel" for the funnel
try to buy a pre-made funnel that ends in 0.25 in diameter
Concerned about water pump control
get two sensors for sensing top and bottom limits
Tips/Solutions on design difficulties on turn table
make the outside walls taller to contain all the water
can make the outside walls so tall as to close the top around the servo
find a commercially available acrylic tube and panels to make the outside walls
Recommendation sections on report
make next steps to improve prototype
Deliverables by the end of quarter
funnel and flow system works
recognition is feasible
turntable works
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Genetically modified mosquitoes unavailable until 3/17 (told prof already)
will have to substitute with colored beads to test CV sorting
will have to use regular mosquitoes to test flow system
Sponsor (Winzeler) wants us to test the entire prototype together, not separate CV sorting and flow system
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent: $100
Remaining: $1,417.49
Progress on Report and Webpage
revising Report and Webpage for second draft due date
sent to be peer-reviewed by Team 1